2.5 Release Planning-9 (20071107)
Attendees
Meeting Agenda
1. Timeline Review
Nov 7 tag 2.5.0.012
Nov 20 2.5.0.beta
Dec 13 2.5.0.RC1 (Release Candidate 1)
Jan 21 2.5.0.RC2 (Release Candidate 2)
Feb 12 2.5.0 Release
2. Goals
Elimination of all outstanding Blocker and Critical bugs for 2.5
Acceptable Performance testing on mysql and oracle databases for Assignments, Resources, Forums, GB & T&Q. What is acceptable? At this point in time, no degradation from performance experienced in 2.4
High degree of verification (85%) of resolved JIRA bugs
Confirmed functional testing on all tools.
Positive feedback from sites running a tagged version of off branch.
Progression
Q: How do we move from Beta? RC?
A: To make the progression from beta to release candidate, the aim is the resolution of outstanding blocker and critical bugs reported.
3. Where we stand
Issues Reported against just 2.5 | 2.5.0.013 | 2.5.0.beta | 2.5.0.rc1 | 2.5.0.rc2 |
|---|---|---|---|---|
Blocker | 4 |
|
|
|
Critical | 20 |
|
|
|
Total | 24 |
|
|
|
All Outstanding tickets (just bugs, no tasks) | 2.5.0.013 | 2.5.0.beta | 2.5.0.rc1 | 2.5.0.rc2 |
|---|---|---|---|---|
Blocker | 3 |
|
|
|
Critical | 58 |
|
|
|
Total | 61 |
|
|
|
Changes in 2.5.0.013
37 tickets - Big chunk of them Assignments. Would like to focus testing there over the next week.