DATE: March 14th
TIME: 12-1:30 PM

AGENDA TOPICS

  1. Decision on final Tool Promotions

    • Tool Promotion Discussions

  2. Proposed Schedule

    • Date to branch: proposal of March 29

    • Tags created Wed after meeting

  3. Time to have daily countdown meetings in prep for release

  4. conversion script - gentle prodding of the dev community

  5. Configuration of QA servers

    • Special properties

    • new additions to OOTB config

  6. refactor of DB - follow up conversation

  7. Chat

NOTES

Tool Promotions- Contrib to Provisional

  • IMS TI: No, but pinging lead

  • Mail tool: Yes.

    • During meeting, it was clarified what some of the responsibilities of a provisional tool was (for instance testing until QA plan is in place). Team was going to meet afterward to ensure they were able to support the move to this status.

    • Will participate in testing until beginning of april when they have a TP available

    • Will be a part of next accessibility review

    • The docs(java and help) will be done by code freeze

  • PageOrderHelper: Yes

  • Polls: Yes

  • Preferable: Not running in prod anywhere.

  • Site Stats: No

    • Still are scalability concerns

  • User Membership: Yes

    • still needs TP, but matrix indcates that the dev of one isn't a prob

    • this is an admin tool that needs a new API prior to introduction to CORE status. There are a # of JIRA's requesting this: SAK-6792. SAK-6793, SAK-6794

Tool Promotions- Provisional to Core

  • Message Center: Yes

  • Post'em: Yes

  • Podcasts: NO

    • Not running at enough places in prod.

    • Some discussion about the marketing value of including this ootb. It was decided that we would separate the tie of provisional/core status from the tools that are exposed in the demo distribution. All tools will be available in this version

    • Indiana will update Maven goal.

  • Roster: Yes

  • Misc Notes

    • Andrew will work with group moving from contrib to provisional to migrate projects in svn

    • Peter will work on migrating contrib projects into JIRA's Sakai project

  • Chat/Chat2

    • there was a lot of debate about this. Sweeping changes that should have been discussed with the community first.

    • current Chat tool has a lot of problems

    • Linda will load test the tool during the QA cycle

    • Some want the old tool and what we've been calling chat2 available at the same time. Implementors will be able to choose between the two

Release Activity Scheduling

  • Branching the release: Will occur March 28th when we tag after QA release meeting

    • There are some components that have already branched (GB, chat).

    • Question asked- Anyone managing their own branches? A: Not really. Chris volunteered to manage OSP and Clay/BU to manage Mailtool.

  • Conversion Scipts

    • Folks are being very good at checking this kind of stuff in

    • ACTION ITEM: lance will ping dev list reminding them to add to this

  • Daily Countdown Meetings

    • Will hold these at 11am during last week of release cycle.