Schedule for Phase 1

Note: All dates below are for 2006.

For a more detailed version of Phase 1 Milestones, please see the Phase 1 Task Spreadsheet

Tentative Phase 1 Schedule:

Dates

Activity

6/15-7/17

Investigation/Design

6/15-9/3

Implementation

9/4-9/10

Test server implementation

9/11-10/1

QA and Usability testing

10/2

Pilot server up and running

Date

Implementation Milestones

8/14

OSID Mock-up completed (Gaurav and Steve)

8/17

Create a citation and put it in Citation List (Jim)

8/25

Populate Citation List from mock search results (Jim)

9/3

OSID implementations return search results to UI (Gaurav, Steve and Jim)

9/10

Server can be run for QA and Usability testing

See also /wiki/spaces/SLIB/pages/2921169027.