Note: All dates below are for 2006.
For a more detailed version of Phase 1 Milestones, please see the Phase 1 Task Spreadsheet
Tentative Phase 1 Schedule:
Dates |
Activity |
---|---|
6/15-7/17 |
Investigation/Design |
6/15-9/3 |
Implementation |
9/4-9/10 |
Test server implementation |
9/11-10/1 |
QA and Usability testing |
10/2 |
Pilot server up and running |
Date |
Implementation Milestones |
---|---|
8/14 |
OSID Mock-up completed (Gaurav and Steve) |
8/17 |
Create a citation and put it in Citation List (Jim) |
8/25 |
Populate Citation List from mock search results (Jim) |
9/3 |
OSID implementations return search results to UI (Gaurav, Steve and Jim) |
9/10 |
Server can be run for QA and Usability testing |
See also /wiki/spaces/SLIB/pages/2921169027.