UI Design and Development Iterations
Info |
---|
See our Planned Iterations page for current stages planned for this project |
Proposed Agile Process
This is the proposed agile development process for the CM project:
- Working Days - CM WG team members set their schedules to work on CM stuff the same days of the week as other team members
- >60% FTE on CM: Monday, Tuesday and Wednesday
- <60% FTE on CM: Tuesday and Wednesday
- "10 at 10" - have 10 minute IM conferences on working days at 10amPDT/1pmEDT:
- What you have accomplished since the last meeting
- What you are working on
- Any questions you may have (Questions are answered one-on-one only after the 10 at 10 meeting is over.)
- Weekly Meetings - use weekly meetings for:
- start each iteration cycle with a UI design walk-through and then delineate the tasks and time estimates onto "Story Cards"
- for checking in on progress and rearranging story cards
...
Info |
---|
Some of this process is borrowed from Menlo Innovations and adapted for our virtual world. For some background on this proposal and their practices, let's all read this excellent paper by next meetinghere are some excellent papers: http://www.menloinstitute.com/freestuff/whitepapers/Project%20Management.pdf |