Note: All dates below are for 2006.
For a more detailed version of Phase 1 Milestones, please see the Phase 1 Task Spreadsheet
Tentative Phase 1 Schedule:
...
Date | Implementation Milestones |
---|---|
8/14 | OSID Mock-up completed (Gaurav and Steve) |
8/17 | Create a citation and put it in Citation List (Jim) |
8/25 | Populate Citation List from mock search results (Jim) |
9/3 | OSID implementations return search results to UI (Gaurav, Steve and Jim) |
9/10 | Server can be run for QA and Usability testing |
...
See also /wiki/spaces/SLIB/pages/2921169027.