Note: All dates below are for 2006.

For a more detailed version of Phase 1 Milestones, please see the Phase 1 Task Spreadsheet

Tentative Phase 1 Schedule:

...

Date

Implementation Milestones

8/14

OSID Mock-up completed (Gaurav and Steve)

8/17

Create a citation and put it in Citation List (Jim)

8/25

Populate Citation List from mock search results (Jim)

9/3

OSID implementations return search results to UI (Gaurav, Steve and Jim)

9/10

Server can be run for QA and Usability testing

...

See also /wiki/spaces/SLIB/pages/2921169027.