- Resources tool feature freeze: July 15
- this will be for settling on the scope of any UI changes we'll consider for 2.5
- probably no more than the pop-up idea IU is floating, but we'll give ourselves a week to think it over and get additional input
- File-picker feature freeze: Aug 1
- for settling the scope of any file picker (attachment helper) changes
- need a little extra time to think through this one, as user expectations are a little murky
- we'll have a focused meeting about this next Tuesday at the same time (4 p.m. GMT, 5 p.m. BST, noon EDT, 9 a.m. PDT)
- Specification freeze*: Aug 15
- final designs/specifications for what will be completed for 2.5
- this will be surfaced to the community as what they can expect to see in the release
- Code freeze: Sept 15
- changes delivered in a working state (i.e. tested to a first order)
- String freeze: Oct 1
- we may not need this, but any message bundle work will be finalized by this point
- Branch freeze: Oct 15
- target for the release as a whole
- Release: Nov 1
...