- UI-03 and 13 - Gonzalo needs some feedback about whether his new work breaks any old schema
- he also needs to know if there are any issues with the way the forms are displayed or work.
- UI-04 - Jim Eng's work that was holding up the show is somewhat done in a new, alternative view of the resources tool. John Ellis will be working on this this week. John will need to do his work and leave a comment in the Jira task and watch Jim's task to ensure that it gets done right. Melissa and Beth will talk with Jim at UMich to make sure that Jim is aware the dependency.
- UI-05 - Not started yet. Chris and John will work on it this week or maybe next week. John will create a Jira task.
- UI-06 - Beth might be working on this one in two weeks.
- UI-07 & 09- Chris has worked on these and will check it in this week.
- UI-08 - Done - John
- UI-10 - Beth may work on this at the end of February. Chris might have time this week.
- UI-11 - Melissa will write more about this requirement this week.
- UI-12 and 14 - No burning need from anyone to get these done. They are no longer assigned to UMich due to staffing concerns.
- UI-16 - UMich needs to discuss about whether this is a priority.
- UI-19 - John needs to connect these Jira's to another bug.
...