Attendees
If you know you will be attending, please list your name
- Megan May (Meeting facilitator)
- Peter Knoop (Sakai project coordinator & regular attendee)
- James Logan (regular attendee)
- Renu (regular attendee)
- David Haines (regular attendee)
- David Horwitz
- Linda Place
- Anthony Whyte
- Jean-François Lévêque
- John F. Hall
- Steven Githens
Meeting Agenda
- Update from Capetown
- Status of Release
- Updates from testers/ developer
- Review open critical/blockers: http://bugs.sakaiproject.org/jira/secure/IssueNavigator.jspa?mode=hide&requestId=11570
- Testing JSR-170
- RC1
Notes on Discussion Points
...
Update From Capetown
Search problem is still outstanding.
---> Seeing JSF with Samigo - stacked threads and the Samigo team.
---> They have seen the problem - load on samigo is a bit higher than the rest. Concurrant load is as high as they'll get. No end user reports. This morings one was traced to a lot of requests from 1 user. SAK-11098
---> Michael asked about the large # of Forums exception reports dropped a lot. David said that the fix has helped a lot.
RC1 Tag
---> Cut the RC1 tag last night 'old style. The problem is, from it he can't create release artifacts. The way to make release artifacts in Maven2 don't . Leverage maven release plug in. he'll redo it all. Should be able to include sighing the Samigo applet. Would take the same revision. In a sense it's like another beta cut and get it up on the QA machines. RC_01. The current tag cut still references m2, old goals. There may be a change to the master pom. doesn't reference the release plug in. There may be a small change in that pom but the rest of them inherit from there.
* David - there are three critical fixes that were merged in. Might want to include them. Change the release candidate. we'll tack on a, b, c to distinguish between the
Review of Open/Critical List
* In the past, Michael has aimed for the next release. Asked Peter to contact him
* David Haines asked about the resolution of a few of the Critical Forum issues (Stats and Groups/Performance). Updates on these are that there is ongoing work on the groups/performance, but there are not resources for working on the Stats. Michael encourage folks to contact Lance if they had resources or if the problem was resulting in a lot of pressure from their stakeholders.
...
Release Status
- Time line Review - Beta2 tag cut on 9th. RC1 should be cut and deployed by the time this meeting is held
- Progress -
- There are over 70 bug fixes going in from beta to beta2. We were down to 47 awaiting verification last week. This week there are 39 awaiting verification
- We're seen a lot of progress in the list awaiting verification.
- % Bugs Verified
Date
- Awaiting Verification
- Awaiting Verification
# Verified
%
1/11/2008
453
720
~61%
1/30/2008
405
773
~66%
- Areas to focus on - http://bugs.sakaiproject.org/jira/secure/IssueNavigator.jspa?mode=hide&requestId=11510
...